VANCOUVER, British Columbia, Aug. 20, 2025 (GLOBE NEWSWIRE) -- via IBN -- ESGold Corp. (“ESGold” or the “Company”) (CSE: ESAU | OTCQB: ESAUF | FSE: Z7D) announced today that it has entered into a binding memorandum of understanding (MOU) with Planta Magdalena S.A.S. (“Planta”), a Colombian corporation, to form a joint venture for the development and reprocessing of fully permitted, gold- and silver-bearing tailings in the Department of Bolívar, Colombia. 

This strategic move represents a significant step in ESGold’s plan to expand its tailings-to-cash-flow model beyond Québec, applying modern, environmentally responsible processing to legacy tailings in one of South America’s most prolific gold-producing regions. The Company aims to generate high-margin, scalable production while delivering environmental remediation benefits and positioning itself for further growth across the Americas.

Deal Highlights

  • Structure & Consideration: ESGold will contribute C$1.5 million for a 50% JV interest and will hold a first right of refusal to purchase the remaining 50% within 12 months at fair market value determined by independent third-party appraisal.
  • Permitting: Planta advises that it holds permits to commence tailings production. ESGold will conduct independent verification of all permits and licences as part of its due diligence prior to entering into a definitive agreement.
  • Strategic Rationale: The Bolívar JV is designed to replicate ESGold’s low-capex, high-margin tailings model developed at Montauban (Québec), while remediating legacy mine sites and improving environmental outcomes for local communities.
  • Fast-Track Workplan: Preliminary due-diligence fire-assay sampling of tailings (27 samples) has been completed. Concentrate tests on the assayed tailings are being finalized at Montauban and will be shipped to ACTLABS in Val-d’Or for analysis. On-site geological and metallurgical visits are being scheduled to finalize the proposed circuit and recovery parameters.
  • Path to Production: Subject to a definitive agreement, verification, and commissioning, the Company’s objective is to add a second high-margin operation alongside Montauban, with a target start-up in 2026.

“Bolívar has a long and storied history as one of Colombia’s most prolific gold-producing regions, with decades of artisanal and small-scale mining contributing significantly to the country’s overall output,” said Gordon Robb, CEO of ESGold. “The region still processes hundreds of thousands of tonnes of ore annually, yet much of it is handled using rudimentary mercury amalgamation methods that leave behind a substantial amount of gold and silver in the tailings. This creates an immense opportunity for ESGold to apply modern, environmentally responsible recovery technology that can significantly improve yields while remediating legacy mine sites. The early validation from our due-diligence sampling is highly encouraging, and it underscores the scalability of our tailings-to-cash-flow model as we aim to build a second high-margin operation in one of the most prolific gold-bearing districts in all South America.”

Planta

Initial Due-Diligence Sampling
As part of joint ESGold–Planta due diligence, 27 tailings samples were collected across the tailings sector and submitted to ACTLABS. Highlights (sample IDs as received) include:

  • SS806: 42.683 g/t Au
  • SS816: 19.284 g/t Au
  • SS817: 18.332 g/t Au
  • SS825: 10.787 g/t Au

In total, 8 of 27 samples assayed above 5 g/t Au, including several high-grade results; multiple samples also returned notable silver values exceeding 190 g/t Ag.

       
 Analyte SymbolAuAuAgAg 
 Unit Symbolppmg/tonneppmppm 
 Detection Limit0.0050.0300.200.20 
 Analysis MethodEF-AAFA-GRAAR-AA8-AR-AA 
 SS8005.689 19.52  
 SS8014.625 9.75  
 SS8023.169 2.60  
 SS8033.532 5.49  
 SS8040.426 4.43  
 SS8050.339 5.14  
 SS806> 10.00042.683> 100.00194.90 
 SS8070.963 2.37  
 SS8085.007 4.37  
 SS8090.692 1.32  
 SS8100.798 1.52  
 SS8111.408 2.48  
 SS8120.862 0.95  
 SS8130.594 2.99  
 SS8143.811 4.25  
 SS8150.584 0.24  
 SS816> 10.00019.28442.60  
 SS817> 10.00018.33244.67  
 SS8188.812 1.23  
 SS819< 0.005 < 0.20  
 SS8202.586 6.64  
 SS8212.417 7.10  
 SS8222.539 6.37  
 SS8232.018 9.64  
 SS8246.790 > 100.00234.34 
 SS825> 10.00010.787> 100.00280.63 
 SS8260.181 0.50  
       

Cautionary Note: The samples referenced above are selective in nature, were collected for due-diligence screening, and may not be representative of the tailings as a whole. No mineral resource or reserve is being declared. Additional systematic sampling, QA/QC, and metallurgical test work are required to determine grade continuity, recoveries, and economic parameters. Results will be disclosed following Qualified Person (QP) review.

ESGold is finalizing bulk-sample concentrate tests to confirm recovery rates for the proposed mining circuit. Testing will be completed at the Company’s Montauban facilities with confirmed assays at ACTLABS in Québec on an expedited basis.

Why Bolívar, Colombia
The Department of Bolívar is recognized as one of Colombia’s most prolific gold-producing regions, with a mining tradition that spans centuries. Today, artisanal and small-scale miners in the region collectively process an estimated 300,000 tonnes of ore annually, producing approximately 128,000 ounces of gold. Despite this significant output, much of the material is processed using rudimentary mercury amalgamation methods, which typically recover less than half of the contained gold and silver.

This long-standing reliance on outdated technology leaves a substantial portion of precious metals unrecovered in the tailings. Modern, mercury-free processing techniques can materially improve recovery rates while eliminating the environmental harm caused by mercury. The combination of a large, continuous feed of tailings, a skilled local workforce, and the region’s established mining infrastructure creates a unique opportunity to launch a high-margin, environmentally responsible operation with near-term scalability potential.

By starting in Bolívar, ESGold positions itself to demonstrate the economic advantages of its tailings-to-cash flow model in one of South America’s most prolific gold-bearing districts, while delivering tangible environmental remediation benefits to local communities.

“The Bolívar opportunity perfectly fits our vision for ESGold’s growth,” said Paul Mastantuono, Chairman and COO. “This is a permitted project in one of South America’s most prolific gold districts, with the potential to quickly generate high-margin cash flow using our modern, environmentally responsible processing. The initial sample results are encouraging, and we’re eager to complete the next stages of technical and legal due diligence. Our team sees this as a launchpad to scale our proven model across multiple jurisdictions, delivering value for shareholders while making a measurable positive impact in the communities where we operate.”

Next Steps & Conditions

  • Definitive Agreement: Finalize binding terms with Planta Magdalena following the completion of legal, technical, and financial due diligence. This includes title and lien verification, litigation search, licensing and permitting review, and confirmation of compliance with Colombian mining and environmental regulations.
  • Technical Verification: Conduct QP-supervised site visits to the Bolívar project for systematic tailings sampling, full QA/QC protocols, metallurgical recovery testing, and circuit engineering design. The Company foresees this to occur in the beginning of September.
  • Bulk Concentrate Testing: Finalize ongoing bulk-sample concentrate tests from Planta Magdalena to confirm recovery rates for the proposed mining circuit. Testing will be completed at the Company’s Montauban facilities with confirmed assays at ACTLABS in Québec on an expedited basis.
  • Montauban Development: Continue construction and commissioning work at Montauban, where concentrate testing and process fine-tuning are progressing well. A detailed 3D geological model is nearing completion to refine high-priority drill targets, and the updated Preliminary Economic Assessment (PEA) will incorporate enhanced economics to reflect higher metal prices.
  • Implementation Planning: For the Bolívar JV, confirm and validate all operational frameworks, develop a localized community engagement plan, and finalize environmental management measures consistent with ESGold’s clean-processing standards.

Why This Matters to Shareholders
With Montauban fully permitted and under construction in Québec, the Bolívar opportunity marks a pivotal step toward building a scalable, self-funded, high-margin platform for precious metals production across the Americas. By securing permitted tailings projects in prolific mining districts, ESGold can generate predictable, repeatable cash flow that funds exploration and discovery without relying on continual equity dilution. This disciplined model pairs near-term production with the upside of exploration, creating a balance of stability and growth rarely seen in the sector. Coupled with our commitment to environmental remediation and community benefits, this strategy positions ESGold to compound value over time, transforming legacy mine waste into both shareholder returns and lasting positive impact across multiple jurisdictions.
Qualified Person Statement

The technical content of this news release has been reviewed and approved by André Gauthier, P.Geo., a Director of ESGold and a Qualified Person as defined by National Instrument 43-101 – Standards of Disclosure for Mineral Projects. Sampling described herein was conducted for due-diligence screening; independent verification, QA/QC, and systematic work remain outstanding. No mineral resources or reserves are declared.

About ESGold Corp.
ESGold Corp. (CSE: ESAU | OTCQB: ESAUF | FSE: Z7D) is a fully permitted, pre-production gold and silver mining company at the forefront of scalable clean mining and exploration innovation. With proven expertise in Quebec, the Company is advancing its Montauban Gold-Silver Project toward near-term production while unlocking long-term value through strategic redevelopment, modern discovery tools, and sustainable resource recovery. Montauban, located 80 km west of Quebec City, represents a blueprint for cash-flow-generating legacy site redevelopment across North America. 

For more information, please contact ESGold Corp. at +1-888-370-1059 or visit esgold.com for additional resources, including a French version of this press release, past news releases, a 3D model of the Montauban processing plant, media interviews, and opinion-editorial pieces.
Stay connected by following us on X (formerly Twitter), LinkedIn, and joining our Telegram channel.

For further information or to connect directly, please reach out to Gordon Robb, CEO of ESGold Corp. at gordon@esgold.com or call 250-217-2321.

On behalf of the Board of Directors
ESGold Corp.
Paul Mastantuono
Chairman & COO
info@esgold.com
+1-888-370-1059

Cautionary Note Regarding Forward-Looking Information
This news release contains "forward-looking information" within the meaning of applicable Canadian securities laws, including statements regarding future production, cash flow, exploration results, project economics, and permitting. Forward-looking information is based on reasonable assumptions that management believes are current but involve known and unknown risks and uncertainties that may cause actual results to differ materially. These risks are detailed in the Company’s public filings on SEDAR+. Readers are cautioned not to place undue reliance on such statements. ESGold disclaims any obligation to update or revise any forward-looking information, except as required by law.

Neither the Canadian Securities Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this release

A figure accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/e167e956-01e3-4243-ad07-65e1b1fad4c7


Primary Logo

Stock Quote API & Stock News API supplied by www.cloudquote.io
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms Of Service.